10 Contents241-5101-200 R2.2
11Passport 8250 Installation Guide R2.2About this documentThis document explains how to install the Passport 8250 device.This document uses the term
12 About this document241-5101-200 R2.2• “Replacing hardware” (page 45).• “LEDs” (page 51).• “Standards” (page 55).ConventionsThere are documentatio
About this document 13Passport 8250 Installation Guide R2.2• ...Three dots in a command indicate that the parameter may be repeatedmore than once
14 About this document241-5101-200 R2.2NMS documentsSee the following NMS documents for information on how to monitor andconfigure the Passport 8250
15Passport 8250 Installation Guide R2.2Chapter 1Passport 8250This section describes the Passport 8250 device. You can view the followingtopics in th
16 Chapter 1 Passport 8250241-5101-200 R2.2Figure 1Passport 8250 deviceThe Passport 8250 can be used for the following applications:• Providing me
Chapter 1 Passport 8250 17Passport 8250 Installation Guide R2.2See “Passport 8250 front panel” (page 17) for an illustration of the hardwarecompon
18 Chapter 1 Passport 8250241-5101-200 R2.2Communication portsThe communication ports, which are located on the network board, include aserial por
Chapter 1 Passport 8250 19Passport 8250 Installation Guide R2.2Passport 8250 softwareYou do not have to order software for the Passport 8250. The
20 Chapter 1 Passport 8250241-5101-200 R2.2
21Passport 8250 Installation Guide R2.2Chapter 2Preparing for the hardware installationThis section provides the following procedures for preparing
22 Chapter 2 Preparing for the hardware installation241-5101-200 R2.2— Access is through the use of a special tool, or lock and key, or othermeans
Chapter 2 Preparing for the hardware installation 23Passport 8250 Installation Guide R2.2Table 1Inventory checklistItem Options available Code #Ch
24 Chapter 2 Preparing for the hardware installation241-5101-200 R2.2Getting the tools to mount the chassis in a rackTo mount the chassis in a rac
25Passport 8250 Installation Guide R2.2Chapter 3Installing the Passport 8250 deviceThis section provides the following procedures for installing the
26 Chapter 3 Installing the Passport 8250 device241-5101-200 R2.2• Allow at least 2 inches of ventilation space on both sides of the device asillu
Chapter 3 Installing the Passport 8250 device 27Passport 8250 Installation Guide R2.2Figure 4Attaching mounting brackets to chassisFigure 5Install
28 Chapter 3 Installing the Passport 8250 device241-5101-200 R2.2Mounting the Passport 8250 device on a NEBS or ETSI rack1 Locate the bracket moun
Chapter 3 Installing the Passport 8250 device 29Passport 8250 Installation Guide R2.2Connecting cables to the portsYou have to connect cables to t
Passport 8250InstallationGuidePublication: 241-5101-200Document status: StandardDocument version: R2.2Document date: October 1999Copyright © 1999 Nort
30 Chapter 3 Installing the Passport 8250 device241-5101-200 R2.23 Connect the other end of the DS-1/E1 cable to the far end.Table 2DS-1/E1 pin as
Chapter 3 Installing the Passport 8250 device 31Passport 8250 Installation Guide R2.2Connecting the ethernet port1 Obtain the following equipment:
32 Chapter 3 Installing the Passport 8250 device241-5101-200 R2.23 Connect the other end of the RJ-45 cable to a 10 Base-T ethernet drop orwork st
Chapter 3 Installing the Passport 8250 device 33Passport 8250 Installation Guide R2.2Connecting the ATM uplink port1 Obtain the following equipmen
34 Chapter 3 Installing the Passport 8250 device241-5101-200 R2.2Figure 7Dual power supply1 Obtain the following equipment:• A -48 v DC power supp
Chapter 3 Installing the Passport 8250 device 35Passport 8250 Installation Guide R2.2The central contact is designated as the chassis ground.4 Con
36 Chapter 3 Installing the Passport 8250 device241-5101-200 R2.2Exit and secure all cables to the left as illustrated in “Cables left of chassis”
37Passport 8250 Installation Guide R2.2Chapter 4Configuring the Passport 8250 for operationsThis section provides the following procedures for configu
38 Chapter 4 Configuring the Passport 8250 for operations241-5101-200 R2.2a. For each power supply module, turn the power supply breaker to ON.The
Chapter 4 Configuring the Passport 8250 for operations 39Passport 8250 Installation Guide R2.2See “Boot command parameters” (page 39) for the boot
40 Chapter 4 Configuring the Passport 8250 for operations241-5101-200 R2.24 For host inet, type the IP address of the remote host.5 If the remote
Chapter 4 Configuring the Passport 8250 for operations 41Passport 8250 Installation Guide R2.2where[set] configures the clocking scheme for the Pas
42 Chapter 4 Configuring the Passport 8250 for operations241-5101-200 R2.2Setting the clocking scheme to External Primary1 Display the clockconfig
Chapter 4 Configuring the Passport 8250 for operations 43Passport 8250 Installation Guide R2.2[E1-1]: clockconfig setExternal Primary Board Number
44 Chapter 4 Configuring the Passport 8250 for operations241-5101-200 R2.2clockconfig [set]2 For External Primary Board Number, enter a board numb
45Passport 8250 Installation Guide R2.2Appendix AReplacing hardwareThis section provides instructions on how to replace hardware components onthe Pa
46 Appendix A Replacing hardware241-5101-200 R2.2Replacing a power supply moduleThe Passport 8250 device is powered by two power supply modules. I
Appendix A Replacing hardware 47Passport 8250 Installation Guide R2.24 Slide the power supply module or dummy power supply filler pack out ofthe sl
48 Appendix A Replacing hardware241-5101-200 R2.2Figure 11Board slots1 For each power supply module, set the power supply breaker to off.2 Flip th
Appendix A Replacing hardware 49Passport 8250 Installation Guide R2.2Passport 8250 board guidelinesUse caution when handling, storing, and transpo
5Passport 8250 Installation Guide R2.2Publication historyOctober 1999R2.2 StandardCommercial availability.
50 Appendix A Replacing hardware241-5101-200 R2.2The fans continue to rotate for a few seconds.4 Remove the new fan module from the package.5 Inse
51Passport 8250 Installation Guide R2.2Appendix BLEDsThe LEDs located on the front panel of the Passport 8250 device. See“Passport 8250 LEDS” (page
52 Appendix B LEDs241-5101-200 R2.2Figure 12Passport 8250 LEDS51 2 34Fan moduleNetwork boardPower supply 1 Power supply 2Service boards8765
Appendix B LEDs 53Passport 8250 Installation Guide R2.2Table 5LEDs descriptionItem color Description1 green on = system initialized and software l
54 Appendix B LEDs241-5101-200 R2.2
55Passport 8250 Installation Guide R2.2Appendix CStandardsThis section describes the standards the Passport 8250 device meets. You canview the follo
56 Appendix C Standards241-5101-200 R2.2— FCC Part 15, Class A (USA)— ICES-003, Class A (Canada)— EN 55022, Class A (Europe)• Immunity, ESD, EFT (
Appendix C Standards 57Passport 8250 Installation Guide R2.2Federal Communications Commission (FCC)The Passport 8250 device complies with Part 68
58 Appendix C Standards241-5101-200 R2.2Before installing this equipment, users should ensure that it is permissible tobe connected to the facilit
59Passport 8250 Installation Guide R2.2CCable connectionsATM uplink port 33Ethernet port 31Serial port 32T1/E1 ports 29Chassis assemblyInstalling on
6 Publication history241-5101-200 R2.2
60 Index241-5101-200 R2.2
Passport 8250InstallationGuideR2.2Copyright © 1999 Nortel Networks.All Rights Reserved.NORTEL, NORTEL NETWORKS, the globemark design, theNORTEL NETWOR
7Passport 8250 Installation Guide R2.2ContentsAbout this document 11Who should read this guide 11What you need to know 11How this guide is organized
8 Contents241-5101-200 R2.2Chapter 2Preparing for the hardware installation 21Selecting an installation site 21Unpacking the Passport 8250 shipment
Contents 9Passport 8250 Installation Guide R2.2Appendix AReplacing hardware 45Replacing a power supply module 46Replacing a board module 47Passpor
Comments to this Manuals